POWER | PROCESS | STRUCTURE | PIPING | PLASMAWELD
Power Plant Work Experience
WORK EXPERIENCE: POWER
1 M/s. SANGHI INDUSTRIERS LTD,
Sanghi, Gujarat
4 Nos of 11.3 MW MAN B&W DG Sets Erection, Levelling & Alignment of DG Sets & its Auxiliaries, Fabrication and Erection of Chimney, Tanks, Ducts and Piping System on Turnkey Basis.
2
M/s. RAMCO GROUP
Rajapalayam, Tamil Nadu.
16 Nos of 900 KW MAN B&W DG Sets Erection, Levelling & Alignment of DG Sets & its Auxiliaries, Fabrication and Erection of Chimney, Tanks, Ducts and Piping System for all the Engines on Turnkey Basis.
3
M/s. AVASARALA POWER PROJECTS
Bangalore, for Kasargod Power Corporation (P) Ltd., Kerala
3 Nos of 7.3 MW Caterpillar Engines Engineering, Supply, Fabrication & Erection 
4 M/s. WARTSILA NSD INDIA LTD.,
Mumbai for M/s. Sterlite Optical Technologies Ltd
Aurangabad, Maharashtra
2 Nos of 6 MW Wartsila DG Sets Erection, Levelling & Alignment of DG Sets & its Auxiliaries. Fabrication & Erection of Ducts & Piping Systems
5
M/s. LAM/s. LARSEN & TUBRO LTD.,
Hirmi Cement Works, Hirmi
RSEN & TUBRO LTD., 
5 Nos of 6 MW Wartsila HFO DG Sets 
Erection,Levelling & Alignment of DG Sets & its Auxiliaries.Fabrication & Erection of Ducts & Piping System.
6
Hirmi CementM/s. LARSEN & TUBRO LTD.,
Gujarat Cements Works, Gujarat.
 Works, Hirmi 
2 Nos. of  6 MW Wartsila HFO  DG Sets
Erection,Levelling & Alignment of DG Sets & its Auxiliaries.Fabrication & Erection Chimney, Tanks,
Ducts & Piping System etc.on Turnkey Basis.Erection,Levelling & Alignment of DG Sets & its Auxiliaries.Fabrication & Erection Chimney, Tanks, 
7 M/s. WARTSILA NSD INDIA LTD.,
Mumbai
For M/s. Reliance Industries Ltd.,Jamnagar,Gujarat.

2 Nos -6 MW Wartsila HFO Dg Sets.
Erection,Levelling & Alignment of DG Sets & its Auxiliaries.Fabrication & Erection Chimney, Tanks,
Ducts & Piping System etc.on Turnkey Basis.
Erection,Levelling & Alignment of DG Sets & its Auxiliaries.Fabrication & Erection Chimney, Tanks,
Ducts & Piping System etc.on Turnkey Basis
Ducts & Piping System etc.on Turnkey Basis.
8 M/s. TATA IRON AND STEEL CO.LTD.,
Sonadih,Raipur.
1 No. – 6 MW Wartsila HFO DG Sets.
 
9 M/s. CHEMPLAST SANMAR LIMITED.,
Plant-II, Mettur Dam.
3 Nos of 6 MW Wartsila HFO DG Sets
Erection, Levelling & Alignment of DG Sets & its Auxiliaries. Fabrication & Erection of Ducts & Piping System.
10 M/s. CHEMPLAST SANMAR LTD.,
Plant-II, Mettur Dam.
6 MW & 4 MW Wartsila 
Erection, Levelling & Alignment of DG Sets & its Auxiliaries. Fabrication and Erection of Ducts & Piping System.
11 M/s. WARTSILA NSD INDIA LTD.,
Chennai  for M/s. West Cost Paper Mills Ltd., Dandeli
4 KW Wartsila DG Set
DG Sets 
Erection, Levelling & Alignment of DG Sets & its Auxiliaries. Fabrication and Erection Chimney, Tanks, Ducts & Piping System on Turnkey Basis.
12 M/s. DAIKAI ENGINEERING (INDIA) P. LTD
Bangalore for M/s. Toyota Technopark India P Ltd. Bidadi, Karnataka 
2 Nos of 800 KW DAIHATSU DG Sets
Erection, Levelling & Alignment of DG Sets & its Auxiliaries. Fabrication and Erection of Chimney, Tanks, Ducts & Piping system on Turnkey Basis.

13 M/s. Gea Energy System (India) Ltd.,
Chennai, for M/s. Aban Power Project,Karuppur. 
120 MW (ISO) CCPP Erection,Testing & Commissioning of Piping (HP & LP) A\and Rotating Equipment
14 M/s. CaterPillar Commercial P.Ltd.,
Hosur Taluk,TamilNadu,for
M/s. Cosmo Films Ltd.,Aurangabad
3 x 6CM32 Power Plant

Supply, Fabrication & Erection of Mechanical Balance of Power Plant on Turnkey Basis
15 M/s. CaterPillar Commercial P.Ltd.,
Hosur Taluk,TamilNadu,
For M/s. JCT Electronics Ltd., Gujarat
1 x 12CM32 (5.35 MW) Power Plant Supply, Erection & Commissioning of Mechanical Balance of Power Plant
16 M/s. Sanghi Industries Ltd., Gujarat 10 MW Power Plant (HYUNDI – HFO 4 X 2.5 MW) Mechanical Fabrication & Erection Works.
17 M/s. kachch Steels P. Ltd., Gujarat

12.5 MW Power Plant (HYUNDI – HFO 5 x 2.5 MW) Mechanical Fabrication & Erection Works.
18 M/s. Wartsila India Ltd., Mumbai, for M/s. Century Enka Ltd., Bhosari 1 x 18 V32 DG Set Erection & Commissioning of all auxiliaries.
19 M/s. Wartsila India Ltd., Mumbai for M/s. Ajanta Manufacturing Ltd., Kutch.
1 x KVGS18G1 Natural Gas Based Power Plant
Erection & Commissioning of auxiliaries
20 M/s. Rolls-Royce Energy Systems India P. Ltd., New Delhi, for M/s. Saheli Exports P. Ltd.,
Mayiladuthurai.
2 x KVGS18G1 Natural Gas Based Power Plant Supply of Fabricated Equipment & Installation & Commissioning of Auxiliary Equipments
21 M/s. Caterpillar Commercial P. Ltd.,
Hosur taulk, Tamil Nadu for M/s. Apollo Tyres Ltd., Baroda.
1 No. Taurus 60 Gas Turbine Based Power Plant Erection & Commissioning of Mechanical Balance of power plant & Piping.
22 M/s. TD Power Systems P. Ltd., Bangalore for M/s. Madras Cement Ltd., Alathiyur 2 x 18 MW Steam Turbine (Coal Fired) based Power Plant Erection, Testing & Commissioning of Power Plant
23 M/s. BGR Energy Systems Ltd., 
Chennai
92.2 MW for Combined Cycle Power Project, Valathur, Phase – II Non – IBR Piping Work
24 M/s. Wartsila India Ltd for Arkey Energy Ltd,  Ramanathapuram 10 x 7.5 MW Gas based Power Plant
Erection, Testing and Commissioning of Engine and all other equipment
25 M/s. Rolls Royce Energy Systems for Penna Electricity Ltd 2 x 6.8 MW Gas Based Power Plant Erection, Testing and Commissioning Engine and all other accessories
26 M/s. Penna Electricity for M/s. Sriba Industries, Chigrukotta 2 x 6.8 MW Gas Based Power Plant

Dismantling and Re-erection, Testing and Commissioning 
27 M/s. Madras Cements Ltd., Ariyalur
1 x 4 MW & 2 x 5 MW Power Plant Dismantling and Re-erection, Testing and Commissioning of Engine and all related equipments